CAN/ULC 1001
Integrated Systems Testing
Fire alarm, sprinklers, elevators, generators, dampers, door holders, maglocks, when these systems are connected, they must be tested together.
1001
The Fast Answers
- What. One coordinated test that proves every life safety system talks to every other one.
- Standard. CAN/ULC 1001, OBC §3.2.10.1, since 2020
- Why. Individual systems can pass alone and still fail together.
- Who needs it. New construction in Ontario where fire protection and life safety systems are interconnected.
- When. End of construction, before occupancy.
- What we do. Plan, test, report, close-out, from start to finish.
REQUIRED FOR YOUR PROJECT?
Since 2020, IST has been required under Ontario Building Code Section 3.2.10.1 for all new construction with fire protection or life safety systems. The 2015 and 2020 National Building Code updates extended this requirement across Canada.
01
New Construction
02
Renovations & Additions
03
Software & Programming Changes
04
Recurring Testing
No Minimum Size
PROCESS
TEST DAY IS UNEVENTFUL BY DESIGN
01
Document Review & Integration Matrix
We collect the design documentation from the project’s engineers and contractors and map every interconnection between fire protection and life safety systems into a single integration matrix. This is where conflicts get caught, while changes are still cheap.
02
Integrated Test Plan
We prepare the test plan the standard requires: cause-and-effect matrix, test scenarios and protocols, notification and personnel safety procedures, and phased-occupancy considerations. Submitted to the AHJ where required.
03
Pre-Test Confirmations
Before test day, every system must already be individually verified: fire alarm verification to CAN/ULC-S537, contractor and verifier confirmations, ESA approval, elevator acceptance. We chase these down so the test date holds.
04
The Integrated Test
UNIO leads the test alongside the trades operating their systems, executing each scenario in the plan. Results land in the matrix live, deficiencies are logged in the room, and the AHJ witnesses where required. Final report and close-out documentation follow for occupancy.
Explore Our Core Services
From early code strategy to sealed engineering design, UNIO supports fire protection projects with practical guidance, clear documentation, and coordinated execution.
FAQ
Frequently Asked Questions
For project-specific guidance, the best next step is to book a consultation with our team.
What is Integrated Systems Testing?
IST verifies that interconnected fire protection and life safety systems operate together as designed. Systems are verified individually during construction; IST proves the connections between them work as one.
When is IST required?
Since 2020, OBC 3.2.10.1 requires IST before occupancy for new construction with interconnected life safety systems, and for renovations that modify existing integrations. The standard calls for retesting at one year, then every five years.
What systems are tested?
Fire alarm and detection, monitoring connections, sprinklers, fire pumps, smoke control, dampers, door holders and maglocks, elevator recall, emergency power, voice communication, and any system designed to operate with them.
Who performs the testing?
An Integrated Testing Coordinator plans and leads the test, trades operate their systems, and the AHJ witnesses where required. UNIO acts as ITC from test plan through final report.
Why does IST matter?
Individual systems can pass their own tests and still fail together. IST catches integration failures before occupancy, while they’re still the contractor’s problem instead of the owner’s.